Coastal Storm Damage Reduction Project (NTB/Surf City - Federal Project)

 

Project initiated:  2002

Estimated Total Cost:  $138,493,000

NTB Share:  $50,000,000

Location (NTB):  South end of North Topsail Beach from CBRA line (approx. 3834 Island Dr.) to Surf City Line.

Coverage Area:  9.9 miles (including Surf City portion)

Amount of Sand:  11.9 million cubic yards (initial construction)

Expected Results:  15' dune 25' wide + 7' berm 50' wide

Renourishment Cycle:  Every 6 years (2.6 million cubic yards of sand)

Status of Project:  On August 27, 2010 the Civil Works Review Board approved the release of the project for final state and agency review (by unanimous vote).  The plan is to have a signed Chief's report December 14, 2010 and a signed Record of Decision by May 2011.  Assuming the project receives a contingent authorization in the Water Resources Development Act in December 2010 and a new construction start in Fiscal Year 2013, the Project Partnership Agreement could be executed by March 2013, with a contruction contract awarded in September 2014 and construction beginning in November 2014.  See below for latest update.

 

LATEST UPDATE: Refer to TISPC monthly reports found on Current Agenda Packet page.

             

Army Corps of Engineers Briefing for Civil Works Review Board

Map & Supplemental Info

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Click map for larger view) 

Town of North Topsail Beach
North Carolina
Town of North Topsail Beach Town Hall
2008 Loggerhead Court
North Topsail Beach, NC 28460
 
Town Hall Admin & Police Dept
TEMPORARILY LOCATED AT
1000 NC HWY 210
Sneads Ferry, NC 28460
  • Facebook Social Icon
  • Twitter Social Icon