New River Inlet Channel Realignment Project (Phase One) 

 

At the January 4, 2012 regular Board of Aldermen meeting the Board made the decision to proceed with Phase One of the Town’s permitted shoreline and inlet management project as proposed by Coastal Planning & Engineering (CP&E).  Phase One includes realigning the New River Inlet Channel and would increase the depth of the channel to approximately 18 feet and widen the channel 500 feet.  Approximately 544,400 cubic yards of sand from the channel will be placed along 9,000 feet of shoreline south of the inlet.   

 

The Town advertised and released the bid documents for the New River Inlet Channel Realignment Project on Friday, August 3rd. Bids were opened on Thursday, September 6 at 2:00 p.m. That night at the regular Board of Aldermen meeting, the project engineers from Coastal Planning and Engineering presented the bids to the Board and recommended the lowest bidder, Marinex Construction Inc.

 

The bid came in below CP&E's estimated cost of $6.5 million at $5,614,160. Marinex indicated that they will be able to start the project at the earliest date possible which will be November 16, 2012. The Board awarded the project to Marinex Construction contingent upon approval of the Town's application to the Local Government Commission for financing of the project (LGC will meet on Oct 2, 2012). Bid Tab Sheet     Project Synopsis





























PROPOSED NRI CHANNEL REALIGNMENT

Channel Width: 500’                  Channel Depth: 18+/-                   Total Material: 635,800 CY

Usable Sand: 544,400 CY        Unsuitable Mat.: 91,400 CY          Length of Project: 9,000 or 1.7 Miles

Sand Grain Size .39”

NEW RIVER INLET CHANNEL REALIGNMENT PROJECT

HAS BEEN COMPLETED

 

Press Release 

 

Presentation by CP&E on Project Completion (Feb 7, 2013)

 

Presentation by CP&E on Post Construction Monitoring (Dec. 5, 2013)


Presentation by CP&E on Post Construction Monitoring (June 5, 2014)


Presentation by CP&E on Post Construction Monitoring (September 3, 2015)


Video about the Project

 


Aerial Photos of the New River Inlet Channel Realignment Project

Click here

 

Additional Pre & Post Pictures

Click here

 

(All pictures courtesy of Aero Photo www.aerophoto.com)

 


 

PROGRESS REPORTS

(below are progress reports submitted

 to the Town by the project engineers)

 

Progress Report 1October 8, 2012

Progress Report 2 - October 22, 2012

 

November 1, 2012 Project Update & What to Expect When Construction Starts

 

Progress Report 3 - November 5, 2012

Progress Report 4 - November 26, 2012

Progress Report 5 - December 5, 2012

Progress Report 6 - December 13, 2012

Progress Report 7 - December 20, 2012

Progress Report 8 - January 14, 2013

 


 

CONTRACT DOCUMENTS FOR

TOWN OF NORTH TOPSAIL BEACH, NC

NEW RIVER INLET CHANNEL REALIGNMENT & BEACH RESTORATION

 

Contract Documents (click here)

Drawings (click here)

New River Inlet Historic Tide Data (click here)

 

Addendum #1 (click here) Posted 8/6

Addendum #2 (click here)    Addendum #2 Bid Schedule (click here) Posted 8/17

Addendum #3 (click here) Posted 8/22

 

Pre-Bid Sign-In Sheet (click here)

 

Bids were opened on 9/6/2012 at opened at 2:00 p.m. (bid tabulation sheet)

 

***It is the sole responsibility of the Bidder to check this web page for any project addenda.

 


SUMMARY OF NEW RIVER INLET CHANNEL REALIGNMENT

PROJECT SCHEDULE

Pre-Construction & Construction Tasks

 

 

Description

Start Date

Completion Date

Jet Probe Survey

Week of 4/15/12

5/4/12

Bathymeteric Survey of New River Inlet

3/23/12

5/4/12

Plans & Specifications

4/2/12

7/27/12

Pre-Construction

Monitoring

10/1/12

12/31/12

Bidding Assistance/

Contract Negotiations

7/9/12

9/28/12

Award Contract

 

October 2012

Construction

No later than

Jan 1, 2013

No later than

Mar 31, 2013